Lakeville Subdivision Construction Resumes

There are certain things you might expect you will have to replace in a year's time, maybe a pair of shoes, or the battery in your smoke detector.

In Lakeville Wednesday, is a very unusual situation.

Crews began replacing an entire sewer system that was only a year old.

Today, a new crew was on site to try and pick up the pieces, to begin replacing sanitary sewer pipes another company buried just a year ago.

They are pipes that apparently warped, because they were not properly bedded.

The game plan was to build 72 high-end homes here, all in the $250,000.00 price range,

But before housing starts here, construction was abruptly halted in 2006.

The setback had some wondering if the project could withstand the financial drain.

So the work that began Wednesday marked the first sign in a long time.

A project designed to compliment the town's new multi million dollar sports park was once again moving forward.